신항남측배후부지

New Port

Southern Hinterland

Construction of the Advanced Logistics Complex

Introduction

  • Location : A designated area of Gangseo-gu, Cheonga-dong, Busan
  • Project period : 2013 ~ 2020 (Stage 2)
  • Area : 1,444,162㎡
  • Project cost : 528.6 billion Won (construction 480.7, others 47.9)
  • Project developer : Ministry of Oceans and Fisheries(Busan Port Construction Office), Busan Port Authority
신항남측배후부지조감도.

Development Direction

  • Construction of a competitive port-supporting hinterland and high-tech logistics complex

Current Status

  • Jan 2013 : Feasibility through (B/C 1.14)
  • May 2013 : Working design commenced (Ministry of Oceans and Fisheries)
  • Jul 2014 : Revised development plan approved (Ministry of Trade, Industry and Energy, no. 2014-117)
  • Oct 2014 : Revised development plan approved, construction plan approved
  • Nov 2014 : Revised development plan approved (Busan Metropolitan City, no. 2014-443)
  • Mar 2015 : Scheme of execution approved

Future plan

  • Dec 2015 : Construction to commence