부산과학산업단지

Jisa

Busan Science & Industrial Complex

Construction of Complex
for the High-Tech & Knowledge Industry

Introduction

  • Location : A designated area of Jisa-dong, Busan
  • Project period : 1992 ~ 2008 (Stage 1-1)
  • Area : 1,962,000㎡ (484.8207ac)
  • Project cost : 235.0 billion Won
  • Project developer : Korea Land & Housing Corporation
  • Expected population : 13,350people
Busan Science & Industrial Complex
 

Development Direction

  • To attract multinational enterprises related to shipbuilding and automotive parts and to create a southeast logistics and high-tech production base
 

Current Status

  • Jan 1993 : Busan Science & Industrial Park Master Plan for posting
  • Dec 1994 : Specify a project implementer(Busan city)
  • Oct 1995 : Implementation plan approval
  • Sep 2001 : Change the project implementer(Busan city->Korea Land Corporation)
  • Jul 2002 : Change the project implementer[Korea Land Corporation -> Korea Land Corporation(Step 1), Busan city(Step 2)]
  • Jun 2006 : completion of Step 1-1(1,622thousand ㎡)
  • Jul 2007 : completion of Step 2(165thousand ㎡)
  • Nov 2008 : completion of Step 1-2(175thousand ㎡)
  • Dec 2008 : completion of the business