Nammoon District

Ungdong

Nammoon District

Creation of the Complex for R&D,
High-Tech Industry and Residential Site

Introduction

  • Location : A part of Nammoon-dong, Jinhae-gu, Changwon city (Gyeongsangnam-do)
  • Project period : 2006 ~ 2014(Stage 1-2)
  • Area : 1,086,000㎡ (268.3564ac)
  • Project cost : 347.8 billion Won
  • Project developer : Gyeongnam Development Corporation
  • Expected population : 15,108people
Nammoon District
 

Development Direction

  • To attract high-tech industrial complex development
  • To provide a pleasant living environment for employees of the New Port
 

Current Status

  • Feb 2007 : Scheme of execution approved
  • Aug 2008 : Site building work started
  • Sep 2010 : Revised development plan and scheme of execution approved
  • Sep 2011 : Revised development plan and scheme of execution approved
  • Aug 2012 : Revision of development plan (for expansion of land for industrial facilities, etc.)
  • Dec 2012 : Revised development plan and scheme of execution approved (For change of land use plan and project period extension)
  • Jan 2013 : Notice of land distribution (202 lots)
  • May 2013 : Revised scheme of execution approved (for revision of land use plan, and division by phase)
  • Jul 2013 : Revised scheme of execution approved (for extension of the first phase project period by two months)
  • Sep 2013 : Revised scheme of execution approved (to reflect final results of first-phase measurement)
  • Nov 2013 : Notice of completion of the first phase
  • Dec 2013 : Revised development plan and scheme of execution approved (for extension of project period by six months)
  • Jun 2014 : Revised development plan and scheme of execution approved (to reflect result of the second phase final measurement)
  • Aug 2014 : Permit for building completion received and completion announced